Rajasthan High Court Criticizes Government Over Delay in Ramgarh Dam Restoration

Jaipur, July 21: The Rajasthan High Court has taken a strong stance regarding the delay in the restoration of the Ramgarh Dam. Senior government officials have been instructed to present a solid plan for the dam’s revival by July 23.
The court emphasized that the historic dam could be revitalized if the government takes the necessary steps. Concerns were raised about ongoing encroachments and disruptions to the natural flow of water in the dam. These directives were issued during a hearing on a petition related to the dam’s restoration, presided over by Acting Chief Justice Sanjeev Prakash Sharma and Justice Bhuvan Goyal.
The High Court directed the secretaries of the Water Resources, Irrigation, and Revenue Departments, along with officials from the Jaipur Development Authority, to appear in person or via video conferencing with a detailed action plan for the dam’s revival on July 23.
During the hearing, amicus curiae Abhinav Sharma informed the court that progress on the ground has been minimal and that the natural water flow in the dam has been severely affected. He urged the court to examine the topography of the catchment area to restore the original drainage system.
Taking these points into serious consideration, the bench observed that encroachments, illegal land allocations, ditches, and permanent constructions have obstructed the dam’s catchment area and the natural pathways of water.
Advocate Karan Rathore, representing local residents, filed a petition to become a party to the case. His counsel, Anshuman Saxena, informed the court that awareness campaigns are being conducted to gather public support for the dam’s revival.
Advocate General Rajendra Prasad, representing the state government, assured the High Court of full cooperation in the restoration efforts. This case has once again highlighted the government’s previous commitments to restore the dam.
Despite assurances from Water Resources Minister Suresh Singh Rawat in the Rajasthan Assembly, progress on key issues, including the investigation of no-objection certificates issued by the JDA and Revenue Department, remains unclear.
A departmental committee formed to investigate the issuance of NOCs for hotels, resorts, agricultural activities, and other constructions in the dam’s catchment area has yet to submit its report. The government has reportedly been unable to take action against alleged encroachments.
Reports indicate that agricultural activities and construction work continue in areas along the Rodha and Madhoweni rivers, affecting the inflow of water into the dam. According to the Water Resources Department, approximately 930 hectares of the dam’s downstream area falls under the jurisdiction of the Jaipur Development Authority.
Officials claim that multiple NOCs were issued for hotel, resort, and other construction projects in these areas. Despite complaints of illegal construction in the downstream area, little action has reportedly been taken.
The High Court is expected to review the government’s restoration plan during the next hearing on July 23. This date could prove crucial for the future of one of Jaipur’s most important water sources.