Mumbai-Ahmedabad Bullet Train Project Gains Momentum, Service Expected by Late 2027

The Mumbai-Ahmedabad bullet train project is progressing rapidly, with a target to launch its first service by late 2027.

New Delhi, November 20 (Daily Kiran) : Central Railways Minister Ashwini Vaishnaw announced on November 20 that the Mumbai-Ahmedabad high-speed rail corridor, India’s first bullet train project, is advancing rapidly beyond mere plans. The goal is to launch the initial service by the last quarter of 2027.

In a detailed statement, Vaishnaw described the 508-kilometer corridor as one of the nation’s most ambitious infrastructure projects. It aims to significantly reduce travel time between two major economic hubs, Mumbai and Ahmedabad.

“The bullet train is no longer just an announcement,” Vaishnaw stated. Construction is progressing at full speed, with the first service expected to begin in late 2027. Once completed, travel time between Mumbai and Ahmedabad will be reduced to under two hours, compared to the current road journey of approximately eight to nine hours.

The minister emphasized that this project is not just about transportation; it will serve as a growth corridor linking several rapidly developing economic centers in Maharashtra and Gujarat. Cities such as Mumbai, Thane, Vapi, Surat, Vadodara, Anand, and Ahmedabad will benefit from increased mobility for people, businesses, and opportunities.

The project gained momentum after Prime Minister Narendra Modi and the Japanese government laid its foundation stone in September 2017. Japan is providing its renowned high-speed rail technology, which boasts a flawless safety record over more than six decades of operation.

However, initial progress was hindered by delays in land acquisition in Maharashtra and the COVID-19 pandemic. Since 2021, construction has accelerated significantly.

Vaishnaw pointed out that the high-speed rail system demands a different level of engineering compared to traditional railways. Designed for speeds of up to 350 kilometers per hour, the trains will operate at around 320 kilometers per hour.

To achieve such high speeds, advanced track technology, braking systems, aerodynamics, track infrastructure, and passenger safety standards are essential. Most of the project will be developed as an elevated corridor, with approximately 465 kilometers of the route constructed as viaducts. This design eliminates the need for level crossings and reduces the risk of animals or unauthorized individuals accessing the tracks.

An added benefit of the elevated design is that road transport and agricultural activities can continue beneath it, minimizing land use impact.

Regarding construction progress, Vaishnaw reported that by September 2026, pier construction was completed over 456 kilometers, and viaduct construction was finished over 371 kilometers. Additionally, over 600,000 noise barriers have been installed across approximately 299 kilometers, and more than 9,300 overhead equipment masts have been erected on 206 kilometers of viaduct.

The project includes the completion of tunneling for four mountain tunnels, with work ongoing on a 21-kilometer tunnel in Maharashtra, of which about five kilometers are complete. Notably, the project also features India’s first underwater rail tunnel beneath Thane Creek.

Vaishnaw announced that civil construction at eight station complexes is complete, with architectural and interior finishing work underway. The construction of rolling stock depots in Sabarmati, Surat, and Thane is also progressing rapidly.