Bhagalpur, November 19 (Daily Kiran) : Adani Energy Solutions Limited (AESL) announced on Thursday that it has secured a transmission project in Pirpainti, Bhagalpur district, aimed at facilitating power evacuation from a new 2,400-megawatt power plant. This project was awarded through a tariff-based competitive bidding (TBCB) process and is expected to generate an annual tariff of ₹500 crore upon completion.
Kandarp Patel, CEO of Adani Energy Solutions, stated that the Pirpainti transmission scheme will establish a robust power evacuation system for the 2,400-megawatt plant. It will also enhance the transmission network in Bihar, thereby improving grid reliability and addressing the state’s growing electricity demand. He emphasized the company’s commitment to developing reliable and efficient transmission infrastructure to support India’s long-term energy security.
The project will be implemented through a special purpose vehicle (SPV), Vikramshila Power Transmission Limited, and is slated for completion by the fourth quarter of 2028. In addition to facilitating power evacuation from the Pirpainti power plant, the project will bolster the state’s transmission network and enhance the reliability of electricity supply.
Upon completion, AESL’s portfolio will include 881 circuit kilometers (CKM) of transmission lines and a transformation capacity of 3,160 MVA. This will increase the company’s total transmission network to 30,683 CKM and its transformation capacity to 146,585 MVA.
The project entails the construction of four gas-insulated substations (GIS) in Jhajharpur, Baithouli, and Begusarai, along with the associated transformation capacity. The transmission infrastructure will consist of the Pirpainti-Jhajharpur, Pirpainti-Begusarai, and Begusarai-Bakhtiyarpur lines at 400 kV, as well as the 220 kV Jhajharpur-Baithouli and Begusarai-Begusarai Town lines.
Additionally, the project will include a loop-in loop-out (LILO) arrangement for existing 220 kV and 132 kV transmission lines in Jhajharpur and the construction of a 400 kV line bay at the Bakhtiyarpur GIS.