Bihars Bhagalpur Reviews Progress of Kayakalp Campaign, Urges Swift Action on Pending Projects
Officials in Bhagalpur review the Kayakalp campaign, emphasizing the need for swift approvals and completion of pending development projects.

Bhagalpur, October 25 (Daily Kiran) : In Bhagalpur, Bihar, the District Magistrate conducted a review meeting on Saturday to assess the progress of various development projects under the Kayakalp campaign. The meeting focused on technical and administrative approvals, budget utilization, the status of construction works, and pending projects.
Attending the meeting were key officials, including the Deputy Development Commissioner, Additional District Magistrate, Municipal Commissioner, Director of DRDA, District Education Officer, District Welfare Officer, Civil Surgeon, and the Executive Engineer of the Public Health Engineering Department.
During the review, it was reported that the Kayakalp campaign encompasses a total of 4,857 works across nine departments, with a budget exceeding ₹20.12 crore allocated for these initiatives.
The meeting highlighted that 1,604 projects are awaiting technical approval, while 2,746 require administrative clearance. To date, 91 projects have received approval, 267 are underway, and 68 have been completed.
The District Magistrate instructed the relevant departments to expedite the approval processes for both technical and administrative aspects. He emphasized that delays in approvals should not hinder development work.
Officials were directed to coordinate effectively to complete all tasks within the set deadlines. The District Magistrate also stressed the importance of regular monitoring of renovation and new construction projects, maintaining quality standards, and ensuring timely completion.
He underscored that it is the responsibility of all involved departments to prioritize the swift execution of pending projects and to conduct regular reviews of the current status of works, submitting progress reports periodically.