Under Pradhan Mantri Gram Sadak Yojana, 1858 roads of length 11,517 km and 84 bridges have been completed in Jammu & Kashmir

Pradhan Mantri Gram Sadak Yojana, is a flagship program of Govt. of India for providing connectivity to unconnected habitations, based on census 2001. In the UTs of J&K and Ladakh, all unconnected habitations of population above 250, are eligible under the program. In the UT of Jammu & Kashmir, 3,261 roads of length of 19,277 km and 243 bridges have been sanctioned, out of which 1858 roads of length 11,517 km and 84 bridges have been completed. Similarly, in the UT of Ladakh, 142 roads of length of 1207 km and 3 bridges have been sanctioned, out of which 96 roads of length 699 km and 2 bridges have been completed till July 2020. Works for connecting 2,149 eligible unconnected habitations were sanctioned in the UT of Jammu and Kashmir, out of which 1,858 habitations have been connected. In the UT of Ladakh, works for 65 eligible habitations were sanctioned and 64 habitations have been already connected by July 2020.

 

Large number of sanctioned road works could not be started by August 2019, because of non- availability of clearance from forest department. However, substantial numbers of such pending cases have been resolved, and works have been awarded and started during last one year, with changes in the governance system. During last one year, 181 number of road works of length 1,292 km and 11 bridges have been completed, with an expenditure of more than Rs 715 Crores.

 

Following two cases are presented as good examples of development of road works under Pradhan Mantri Gram Sadak Yojana (PMGSY).

 

Upgradation of Link Road from T03 to Stok (PMGSY Leh)

Length: 11.70 Kms, Sanctioned Cost: Rs. 1299.78 Lacs

 

The road proposed to village Stok in district Leh, takes off from km 2nd of Choglamsar Hemis road to Stok village for a length of 11.70 Kms benefitting a population of 1855, as per 2001 census. This scheme was sanctioned under PMGSYS-I, in the year 2018-19 (Phase XII). The earlier road was in a damaged condition and was not serving as all weather road. This road is being constructed by using plastic waste for the first time in the entire Leh district. In this technology, the waste plastic is used in shredded form, and is pushed into the hot mix plant over the heated aggregates. The plastic melts and coats the heated aggregates, before the aggregates are coated with hot bitumen. This technology will reduce the plastic waste and also strengthen the pavement structure of the road, by reducing the water absorption of aggregates. This project was started in the year 2019 and length of 7 Kms has been completed up to Bituminous Surface level and the balance length is in progress and shall be completed by October-2020. By upgradation of the road, the habitants of the village Stok will get all weather connectivity with the nearest market due to which the socio-economic conditions of the habitants will be improved. During summer, thousands of tourists go to this village to visit the Museum in Royal palace, Stok Monastery and also the start point of the trek route to Stok Kangri which is a major tourist attraction.